Every location
Overview
9 people recorded work at 4 locations
Sep 11 to Oct 8
Units completed
950
over 23 working days
People reporting
9
across 4 locations
Units per day
Busiest: Sep 18, 74 units
Sep 14
Sep 21
Sep 28
Oct 5
Downtime split
27 h total
Hardest hit: North Unit, 12.5 h
By location
- 132034% share
- 222624% share
- 321623% share
- 418820% share
By work code
Top 3
- 1WLD · Weld check22838% share
- 2BJ · Bolted joint check18932% share
- 3RT · Film review18130% share
By person
- 116718% share
- 213615% share
- 312313% share
- 412113% share
- 511913% share
- 610511% share
- 7809% share
- 8758% share
Latest work
163 records
- Thu8OctWLDWeld check7 units3:28 PM
- Thu8OctWLDWeld check3 units3:17 PM
- Thu8OctBJBolted joint check2 units12:49 PM
- Thu8OctRTFilm review2 units11:31 AM
- Thu8OctVTVisual walkdown4 units9:47 AM
- Thu8OctRPTReport package1 unit9:26 AM
- Thu8OctBJBolted joint check2 units7:03 AM
- Wed7OctVTVisual walkdown7 units12:47 PM
- Wed7OctRPTReport package1 unit12:16 PM
- Wed7OctWLDWeld check10 units11:56 AM
Barge loading arms, east berth
- Wed7OctUTTThickness shots10 units10:10 AM
Both sides of the header crossover
- Wed7OctWLDWeld check9 units8:25 AM
Latest downtime
14 records
- Waiting2.5 h
Escort for the restricted area was not available
Wed, Oct 7 - Waiting1 h
Lightning hold, everyone off the structures
Tue, Oct 6 - Waiting2 h
Permit renewal ate most of the morning
Mon, Oct 5 - Waiting1 h
No bucket truck free until after lunch
Thu, Oct 1 - Unplanned3 h
Witnessed a last-minute hydrotest on a new spool
Wed, Sep 30 - Waiting1.5 h
Gas test needed before entry, tester was across the plant
Tue, Sep 29 - Waiting2.5 h
Operations asked us to hold until the line was drained
Fri, Sep 25 - Unplanned1 h
Covered a walkdown for another crew that was short a person
Fri, Sep 25 - Unplanned2.5 h
Checked a hose connection after a near-miss report
Thu, Sep 24 - Waiting1 h
Scaffold on the cooling tower deck not tagged until 10
Wed, Sep 23