Unit 4 Crude Turnaround

Gulf Bend Refining · Port Allen, LA · Jun 29 to Jul 24
Total equipment
50
4 asset groups
Complete
14
28% of scope
Open RRs
6
awaiting disposition
Inspectors
10
on site
Click a step cell to stamp your initials and date. Click again for N/A, again to clear. Click the status pill to advance it.
Eqpt. #DescriptionStatusInternal VIUT-TNDERRRR Comp.OK to CloseReport CompleteFinal QAComments
Overhead accumulatorMR 7/6SO 7/8WS 7/10····Ladder clip finding, see RR
Reflux drumJK 7/11CL 7/1AC 7/3·MR 7/5SO 7/7WS 7/9DF 7/11
Flash drumRT 7/4PN 7/6GH 7/8JK 7/10CL 7/12AC 7/2MR 7/4Pitting repaired, RR closed
Suction knockout drumSO 7/9WS 7/11DF 7/1·····
Surge drumCL 7/2AC 7/4MR 7/6SO 7/8···Nozzle N4 flange face, see RR
Amine flash drumPN 7/7GH 7/9······
Fuel gas KO drumWS 7/12DF 7/2RT 7/4·PN 7/6GH 7/8JK 7/10CL 7/12
Deethanizer feed drum········
Condensate collection drumGH 7/10JK 7/12······
Vent scrubber drum········
Steam separator drumMR 7/8SO 7/10N/A·DF 7/2RT 7/4PN 7/6GH 7/8
LPG surge bulletJK 7/1·······
Sour water degassing drumRT 7/6PN 7/8GH 7/10·····
Blowdown drum········