Digital wallchart
Unit 4 Crude Turnaround
Gulf Bend Refining · Port Allen, LA · Jun 29 to Jul 24
Total equipment
50
4 asset groups
Complete
14
28% of scope
Open RRs
6
awaiting disposition
Inspectors
10
on site
Click a step cell to stamp your initials and date. Click again for N/A, again to clear. Click the status pill to advance it.
| Eqpt. # | Description | Status | Internal VI | UT-T | NDE | RR | RR Comp. | OK to Close | Report Complete | Final QA | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Overhead accumulator | MR 7/6 | SO 7/8 | WS 7/10 | · | · | · | · | Ladder clip finding, see RR | |||
| Reflux drum | JK 7/11 | CL 7/1 | AC 7/3 | · | MR 7/5 | SO 7/7 | WS 7/9 | DF 7/11 | |||
| Flash drum | RT 7/4 | PN 7/6 | GH 7/8 | JK 7/10 | CL 7/12 | AC 7/2 | MR 7/4 | Pitting repaired, RR closed | |||
| Suction knockout drum | SO 7/9 | WS 7/11 | DF 7/1 | · | · | · | · | · | |||
| Surge drum | CL 7/2 | AC 7/4 | MR 7/6 | SO 7/8 | · | · | · | Nozzle N4 flange face, see RR | |||
| Amine flash drum | PN 7/7 | GH 7/9 | · | · | · | · | · | · | |||
| Fuel gas KO drum | WS 7/12 | DF 7/2 | RT 7/4 | · | PN 7/6 | GH 7/8 | JK 7/10 | CL 7/12 | |||
| Deethanizer feed drum | · | · | · | · | · | · | · | · | |||
| Condensate collection drum | GH 7/10 | JK 7/12 | · | · | · | · | · | · | |||
| Vent scrubber drum | · | · | · | · | · | · | · | · | |||
| Steam separator drum | MR 7/8 | SO 7/10 | N/A | · | DF 7/2 | RT 7/4 | PN 7/6 | GH 7/8 | |||
| LPG surge bullet | JK 7/1 | · | · | · | · | · | · | · | |||
| Sour water degassing drum | RT 7/6 | PN 7/8 | GH 7/10 | · | · | · | · | · | |||
| Blowdown drum | · | · | · | · | · | · | · | · |