All sites overview
4 active sites · 9 inspectors reporting
Activity per day
Jul 1 to Jul 13By site
- 1452 inspectors
- 1203 inspectors
- 1023 inspectors
- 753 inspectors
By inspector
- 953h blocker · 0h break-in
- 810.5h blocker · 0h break-in
- 640.5h blocker · 0h break-in
- 54
- 451.5h blocker · 0h break-in
- 380h blocker · 4h break-in
- 360.5h blocker · 0h break-in
- 251.5h blocker · 6h break-in
- 4
Calendar
Click a day to see its logs below
July 2026
Recent activity
| When | Inspector | Activity type | Site | Count | Note | |
|---|---|---|---|---|---|---|
Jul 13 4:06 PM | Radiography review | 8 | ||||
Jul 13 3:51 PM | Flange and valve checks | 6 | ||||
Jul 13 2:03 PM | UT thickness readings | 2 | ||||
Jul 13 1:59 PM | Flange and valve checks | 5 | Unit 3 crossover piping | |||
Jul 13 11:29 AM | Weld inspection | 10 | North rack, circuits 12 to 18 | |||
Jul 13 10:17 AM | Pipe inspection | 11 | ||||
Jul 11 1:22 PM | UT thickness readings | 2 | ||||
Jul 11 11:42 AM | UT thickness readings | 5 | ||||
Jul 11 7:51 AM | Weld inspection | 7 | ||||
Jul 10 4:47 PM | Flange and valve checks | 3 | ||||
Jul 10 12:42 PM | Radiography review | 3 | ||||
Jul 10 9:57 AM | Radiography review | 1 | ||||
Jul 10 8:04 AM | UT thickness readings | 8 | Night shift turnover items | |||
Jul 9 4:08 PM | Flange and valve checks | 1 | ||||
Jul 9 3:03 PM | Flange and valve checks | 11 | ||||
Jul 9 1:01 PM | Radiography review | 4 | ||||
Jul 9 12:36 PM | Weld inspection | 8 | New spool pieces in the laydown yard | |||
Jul 9 10:32 AM | Flange and valve checks | 7 | ||||
Jul 9 10:01 AM | Pipe inspection | 10 | ||||
Jul 9 7:26 AM | UT thickness readings | 11 | Tank farm walkdown, rows A and B |
Recent interruptions
10 entries- BREAK-IN
Called over to verify a weld repair before backfill
3h···Jul 13 · 3:19 PM
- BLOCKER
Waiting on a fire watch to free up
0.5h···Jul 13 · 9:02 AM
- BREAK-IN
Emergency UT shots on a pump discharge line
4h···Jul 9 · 3:58 PM
- BLOCKER
Operations would not release the line for inspection until 2 pm
1.5h···Jul 9 · 3:44 PM
- BREAK-IN
Pulled off the planned route to check a leaking flange on the dock line
2h···Jul 8 · 1:26 PM
- BLOCKER
Permit desk backed up, no hot work permit until after lunch
3h···Jul 8 · 9:39 AM
- BLOCKER
Waiting on scaffolding at Unit 4, could not reach the upper welds
0.5h···Jul 6 · 10:21 AM
- BLOCKER
Client rep unavailable to walk the punch list
1.5h···Jul 2 · 11:43 AM
- BREAK-IN
Diverted to walk down a steam leak with operations
1h···Jul 1 · 1:36 PM
- BLOCKER
Site siren drill, all work stopped for two hours
0.5h···Jul 1 · 10:47 AM